Amag-Diana City excavation trench, Schaffhausen
A 12 metre-deep excavation trench with vertical excavation trench closures on all sides was created in the centre of Schaffhausen for the new commercial building with showrooms and a three-level underground car park of Amag-Diana City.
- Building contractor: AMAG Automobil- und Motoren AG, Schinznach Bad
- Customer: AG Ernst Hablützel & Co., Wilchingen
- Project designer: Bona + Fischer Ingenieurbüro AG, Winterthur
- Construction site supervision: ixtegra ag, Schaffhausen
- Implementation: May 2009 – October 2009
Map
Divisions performance
Foundation engineering.
Specific figures
Retaining wall beams57 units at 10-12 m, ø 700 mm
Temporary anchors122 units at 15-25 m, Po = 300 - 440 kN
Shotcrete1,400 m2, 550 m3 loose
Underpinning10 micro-piles, head pretensioned with flat presses / 75 floor nails
Water retention3 filter wells ø 700 mm, 350 m2 sheet pile wall boxes